It all starts with an idea and an empty space... but quickly the Bricking It apartment starts to take shape.
Planning Ahead
Weeks 1 to 3
Like all good building projects, it pays to plan ahead...
Risk Management >
Interior Design >
Watch the video >
Even at this early stage Dr Phil is chasing up the delivery of materials plumbing and electrical materials they won't need on-site for weeks. The kitchen is already on order, even though we won't be installing it until Week 13.
Now that work is underway Dr Phil will re-assess which tradesmen and trainees are in which rooms. He wants to avoid congestion as far as possible.
A week-by-week count-down sheet is pinned in the trainees' social area. Deadlines are never far away.
< Previous: Weeks 1 to 3 Next: Weeks 4 to 6 >
What do you have to do transform an empty shell into a luxury apartment? Find out here >
Why do standards matter at work? Find out here >
Check out our job profiles here >
Check out our experts
Project Manager >
Designer >
Construction Mgr >
Plumber 1 >
Sparky >
Tiler >
Painter/Decorator >
Plasterer >
Chippy >
Plumber 2 >